Laos todayFigures from official sources · checked 26 Nov 2026, 14:09
Exchange rates · kip
BuySell
US dollar22,34922,683
Thai baht665.15678.43
Chinese yuan3,3483,414
BCEL · 26 Nov 2026
Fuel · kip per litre
95Gasoline 9534,340
91Regular 9129,560
DSLDiesel29,520
Lao State Fuel · from 26 Nov 2026
Gold
1 baht · sell40,260,000
1 baht · buy39,730,000
World · USD/oz3,588.79
Lao Gold Association · 26 Nov 2026, 19:45
Weather · Vientiane
27°C

Partly cloudy · tomorrow 21–30°C

Vientiane Capital · updated 14:09
Local News

Oudomxay inspects pending Laos-China railway impacts

A joint inspection team reviewed outstanding Lao-China railway impacts in Oudomxay province, noting 41 unresolved environmental and social cases.

Vientiane Post News Desk26 November 2026, 09:46 · 2 min read9 views
Oudomxay inspects pending Laos-China railway impacts
Listen to this storyAI voice · female · 4 min
0:00 / 03:43

During November 2026, an inspection team from the State Inspection Authority and the Railway Department, led by Phonkeo Sihomvong, Deputy Director General of the State Inspection Department of the State Inspection Authority, conducted a follow-up, inspection, and pushed for the resolution of remaining impacts from the Lao-China Railway project at the Xay District Passenger Station meeting room in Oudomxay province, with the participation of relevant departments, national defense and public security officials, and station customs officers.

Summary of compensation progress and remaining issues

The construction project of the Lao-China Railway passing through Oudomxay province has a total length of 123.60 kilometers, covering an area of 812.30 hectares across 44 villages, with a total of 1,685 affected families (3,047 land plots), with operational details as follows:

  • Compensation budget side: The province received a total budget of 253,579,701,863 kip (229.98 billion kip from the government budget and over 23.59 billion kip from the railway company budget). Currently, 1,684 families have been disbursed compensation amounting to 230,451,050,271 kip (leaving 1 family worth 86,665,000 kip who has not yet come to collect it). The remaining over 23.12 billion kip is due to the fact that land compensation mediation at Namor Station and Nga Station has not yet been completed according to the design.
  • Environmental and social issues: There are still 41 cases that have not yet been resolved, such as the railway cutting through people’s agricultural access roads, 30 cases of rocks dumped onto people’s land, water stagnation issues at the railway underpass in Xay district, and soil erosion during the rainy season that causes transportation difficulties.
  • Encroachment on reserved zones: It was discovered that some people have been conducting agricultural activities in the area above the tunnel, along the edges of the tunnel, setting up huts, and grazing livestock along the railway corridor, which poses safety risks.

Resolution directions and strict measures

At the end of the meeting, Phonkeo Sihomvong emphasized that all sectors pay attention to implementing 4 important tasks:

  1. Maintain security and prevent theft: Instruct the Railway Department to coordinate with national defense and public security forces to step up strict inspections around the station and prevent the illegal cutting or purchasing of cables and equipment of the Lao-China Railway.
  2. Clear demarcation: Instruct relevant departments to re-survey the actual area and make a joint record to clearly demarcate the reserved corridor zone.
  3. Publicize regulations: Intensify the dissemination of regulations concerning railway work so that the public is thoroughly aware and understands in order to reduce corridor encroachment.
  4. Establish coordination mechanism: Instruct the Lao-China Railway Company to appoint dedicated liaison officers to cooperate and regularly provide passenger and freight transport data to the government sector.

Source: Reported by Sipheng Dalasavanh / State Inspection Authority